The vendor is required to provide ADA compliant observation platform and associated site improvements at, including earthwork, retaining walls, sidewalk, and lawn restoration between and the existing pathway along the grand river.
- Responsible for the proper disposal of any existing material that is excavated and deemed unsuitable by the engineer or in excess of what is required, including the following:
• Stripping of topsoil within the grading limits.
• Earth excavation, embankment and grading for aggregate base, sidewalk and bleachers.
• Backfilling adjacent to sidewalks and retaining walls with engineer approved material.
• Grading for preparation of topsoil surface.
• Removal of solid boulders, one-half cubic yard or more in volume.
• Any required temporary shoring or protective fencing required for the improvements.
- Contract Period/Term: 2 years
- Prebid Conference Date: September 16, 2025
- Questions/Inquires Deadline: September 25, 2025