A government agency in New York issued “Building Management System” (IFB). Solicitation SYS-5610 closed on July 21, 2026. Eligibility: Only for USA Organization. Submissions via Online Portal.
The Vendor is required to provide building management system (BMS) and direct digital control (DDC) systems are comprised of any and all components associated with the BMS-DDC systems operation and the monitoring and control of equipment and devices associated with it.
- The calibration sheet must include, but not be limited to, the following data:
• Equipment description (tag no.);
• System or equipment served;
• Analog range;
• Set point;
• Calibration as-found;
• Calibration as-left;
• Repeatability (over five cycles);
• Test equipment certificate; and
• Date, time, and technician signature.
- The following are examples of parameters to be included in the review:
• Component and equipment failures;
• Water consumption;
• Electrical and fuel consumption;
• Pm observation notes;
• Short and long term repairs and replacements.
- Semi-annual preventive maintenance service
1. Control dampers - controlled and operated by the BMS:
• Inspect inlet guide vanes linkages, set screws and blade adjustment for proper tightness. Lubricate as required.
• Operate inlet guide vanes over full modulation range to ensure proper operation.
• Adjust as required.
• Clean all dampers.
• Inspect edge and jamb seals for damage or wear.
• Inspect damper linkages, set screws and blade adjustment for proper tightness.
• Adjust linkages for tight close-off.
• Lubricate as required.
• Operate dampers over full modulation range to ensure proper and non-binding operation.
• Clean and adjust for smooth operation.
• Inspect condition of damper actuator, fittings, and related tubing for leaks.
2. Control valves - controlled and operated by the BMS:
• Verify that control valves are providing tight shut-off of controlled medium.
• Inspect condition of the valve and actuator.
• Leaks are to be repaired including tightening or replacement of valve packing.
• Operate control valve and actuator over full design modulation range to verify proper operation. Adjust as necessary.
• Verify proper operation of all pilot positioners.
- Corrective action based maintenance – building management system (BMS) / direct digital control (DDC)
• Review the log book entries;
• Sign in and sign out using the trouble book repair log
• Indicate the amount of time the technician was onsite to address the trouble book entries;
• Troubleshoot the issues identified and perform the applicable maintenance tasks listed below, on the problematic component(s), e.g.; sensor, control valve, control damper, operating sequence and scheduling, etc.
- Building management system (BMS-DDC)
1. Calibration requirements:
• Equipment description (include tag no.);
• Area served;
• Analog range;
• Set point;
• Calibration, as-found;
• Calibration, as-left;
• Verification of repeatability over five cycles;
• Date and time verification or calibration performed;
• Technician signature.
2. Verify operation of and calibrate the following:
• Heating and cooling system resets and demand
• Programmable controllers and control loops;
• Verify the sequence of operation:
o Startup sequence;
o Supply air flow control;
o Return air flow control;
o Outdoor air flow control;
o Supply air temperature;
o VAV control;
o Vane control;
o Mixed air temperature;
o Economizer cycle;
o Shut down sequence;
o Hot water heating system;
o Chilled water system;
o Perimeter zone control;
o Purge mode.
Ask any question about the RFP and its amendments. Instantly surface schedules, deliverables, compliance items, evaluation criteria, and budget details with 100% source-backed answers.
Quick answers about deadlines, eligibility and submission for this solicitation.
No. This opportunity (SYS-5610) closed on July 21, 2026. See similar open RFPs below.
A government agency in New York. The buyer's contact and submission details are in the solicitation documents.
Only for USA Organization.
Submissions are accepted via Online Portal. Follow the instructions in the solicitation documents.
Contract term: 3 years.
Yes: Mandatory on June 29, 2026.
Questions and inquiries must be submitted by July 7, 2026.