The vendor is required to provide that
• 2 locations at its central facility and operations facility that need additional networking locations.
• Central will require 2 additional networking runs per the engineering drawings supplied.
• Operations center will require 10 cat 6 runs from its networking room to its dispatch office.
• 4 cat 6 runs to the training room installation of 1 additional plywood wall panel and grounding stud in its networking room.
• Networking and power cover plates and or keystones will be colored differently from existing outlets.
• Installation of supplied networking cabinet contractor will be required to provide and install ladder and earthquake ties to opposing walls and existing network cabinets.
• Contractor will supply and install a new 24 port patch panel for termination of the 14 runs in the new proposed cabinet in the networking room.
• contractor shall obtain and pay for all construction permits, licenses, and certificates of occupancy required.
• All work and related work for site cleanup and site restoration.